Full rewire of a Victorian terrace

A period property taken from rubber-sheathed legacy wiring to a fully compliant installation, room by room, while the family stayed in the house.

Placeholder — finished consumer unit
22
Circuits
9 days
Duration
EIC + Part P
Certification
Included
Making good

Scope of works

  • Full rewire with minimal-damage chasing
  • New 18th Edition consumer unit with SPD
  • Lighting design across three floors
  • Smoke and heat detection to BS 5839-6
  • EICR and Part P certification

Outcome

Completed in phases so the household kept power and heating throughout; every circuit tested and certified on handover.

Every project is handed over with full test certification, an as-installed schedule and a documented aftercare route.